- Cirata Floating Photovoltaic Power Plant scheduled to begin commercial operation in Q4 2022

- 145-megawatt (ac) plant being developed by PT. Pembangkitan Jawa Bali Masdar Solar Energi – joint venture between Masdar and PT PJBI

ABU DHABI, UAE, Aug. 3, 2021 /PRNewswire/ -- Masdar, one of the world's leading renewable energy companies, and PT PJBI, a subsidiary of Indonesia's state-owned electricity company PT PLN, announced today that financial close has been achieved on the Cirata Floating Photovoltaic Power Plant project and construction work has begun.

Masdar joint venture reaches financial close and starts construction on Indonesia's first utility-scale floating solar power plant Masdar joint venture reaches financial close and starts construction on Indonesia’s first utility-scale floating solar power plant

Financing for the project, Indonesia's first floating solar power plant, was arranged through Sumitomo Mitsui Banking Corporation, Societe Generale, and Standard Chartered Bank. The 145-megawatt (ac) plant is being developed by PT. Pembangkitan Jawa Bali Masdar Solar Energi (PMSE), a joint venture between Masdar and PT PJBI, and is expected to begin commercial operation in the fourth quarter of 2022.

"The Ministry of Investment fully supports the investment realization of the Cirata Floating Solar Project by PT. PJBI and Masdar. This is a flagship project of the UAE's investment in Indonesia, and most importantly, it is in line with the Indonesian Government target in renewable energy mix of 23 percent by 2025," said His Excellency Bahlil Lahadalia, Minister of Investment for the Republic of Indonesia and Chairman of the Indonesia Investment Coordinating Board. "This project represents the UAE's first investment in Indonesia's renewable energy sector, and we look forward to further collaboration between our countries, as we leverage our natural resources to build a more sustainable future."

"Reaching this historic milestone demonstrates the strength of the relationship between Indonesia and the United Arab Emirates," said His Excellency Abdulla Salem Al Dhaheri, Ambassador of the United Arab Emirates to the Republic of Indonesia and the ASEAN region. "The UAE is committed to promoting and investing in clean energy projects around the world, and to taking positive action on climate change. We stand together with Indonesia on driving sustainable development and we will continue to support the nation's clean energy transition."

The plant, set to be the largest of its kind in Southeast Asia and one of the largest in the world, is being built on the Cirata reservoir in the West Java Province. Once completed, it will provide enough electricity to power 50,000 homes, and will offset 214,000 tons of carbon dioxide emissions, and contribute to the creation of up to 800 jobs. Throughout the development of the project, Masdar has conducted a series of social initiatives, raising awareness on sustainability issues and strengthening local community engagement.

"This achievement would not have been possible without the constant support of the Government of Indonesia, our lenders, and our strategic partnership with PJBI and PT PLN, who have been with us on every step of our journey," said Mohamed Jameel Al Ramahi, Chief Executive Officer of Masdar. "The designation of this project as a National Strategic Project (PSN) has been invaluable in enabling us to make such significant progress and demonstrates that the Government recognizes the economic and social benefits the Cirata project will bring to the local community and to all of Indonesia."

"This floating power project is a first for Indonesia, and is also a significant step in PJBI's renewable energy journey," said Amir Faisal, President Director of PJBI. "We see tremendous potential for similar projects in Indonesia and we look forward to continuing our fruitful collaboration with Masdar to work on more renewable energy projects and help our nation achieve its clean energy objectives." 

Indonesia, the world's largest archipelago nation, is targeting 23 percent of its energy mix coming from renewables by 2025 under its Electricity Infrastructure Acceleration Program. The government also recently announced that it aims to increase the proportion of renewable power in its 2021-2030 national electricity plan to at least 48 percent, from 30 percent in its previous plan.

Read more https://www.prnasia.com/story/archive/3461646_AE61646_0

AIIMS Group and AdVisible merge

Two of Australia’s most established independent agencies unite, creating marketing powerhouse backed by three decades of combined experience     ...

Block's layoffs are a design win. Here's why

We spend millions designing features that save users 30 seconds. Block just saved thousands of employees 40 hours a week. That's not a crisis. That's...

Why I Decided to Build a Better Way to Build Homes

Why does building a home still feel like stepping into the unknown? In an industry where costs blow out and decisions come too late, certainty has...

Leonardo.Ai reveals new brand, expanding its creator-first platform for the next era of generative AI

The company has also launched its developer API to empower creators and builders to integrate AI into their workflows SYDNEY, Australia – 19 Febr...

Psychosocial injury risk starts inside workplace microcultures

Psychological injury is now one of the most expensive categories of workers compensation claims in Australia, with Safe Work Australia reporting t...

2025 Thryv Business and Consumer Report - Australian small businesses show grit under pressure

Australia’s small businesses are powering ahead with optimism, resilience and discipline, however, mounting pressures on costs, wellbeing and cons...