Business Daily Media

Why US offshore wind power is struggling – the good, the bad and the opportunity

  • Written by Christopher Niezrecki, Director of the Center for Energy Innovation, UMass Lowell
Why US offshore wind power is struggling – the good, the bad and the opportunity

America’s first large-scale offshore wind farms began sending power[1] to the Northeast in early 2024, but a wave of wind farm project cancellations and rising costs have left many people with doubts about the industry’s future in the U.S.

Several big hitters, including Ørsted, Equinor, BP and Avangrid, have canceled contracts[2] or sought to renegotiate them[3] in recent months. Pulling out meant the companies faced cancellation penalties ranging from US$16 million[4] to several hundred million dollars per project. It also resulted in Siemens Energy, the world’s largest maker of offshore wind turbines, anticipating financial losses in 2024[5] of around $2.2 billion.

Altogether, projects that had been canceled by the end of 2023 were expected to total more than 12 gigawatts of power[6], representing more than half of the capacity in the project pipeline.

So, what happened, and can the U.S. offshore wind industry recover?

A map shows regions with the strongest offshore wind power potential, including off the US and Northern Europe.
Estimates of the mean annual wind speeds in meters per second extending 200 kilometers from shore at a height of 330 feet (100 meters). ESMAP/The World Bank via Wikimedia, CC BY[7][8]

I lead UMass Lowell’s Center for Wind Energy Science Technology and Research WindSTAR[9] and Center for Energy Innovation[10] and follow the industry closely. The offshore wind industry’s troubles are complicated, but it’s far from dead in the U.S., and some policy changes may help it find firmer footing.

Long approval process’s cascade of challenges

Getting offshore wind projects permitted and approved in the U.S. takes years[11] and is fraught with uncertainty for developers, more so than in Europe or Asia.

Before a company bids on a U.S. project, the developer must plan the procurement of the entire wind farm, including making reservations to purchase components such as turbines and cables, construction equipment and ships. The bid must also be cost-competitive, so companies have a tendency to bid low and not anticipate unexpected costs, which adds to financial uncertainty and risk.

The winning U.S. bidder then purchases an expensive ocean lease[12], costing in the hundreds of millions of dollars[13]. But it has no right to build a wind project yet.

A map shows lease areas, from South Carolina to Massachusetts. Continental shelf areas leased for wind power development along the Atlantic coast. U.S. Department of the Interior, 2024[14]

Before starting to build, the developer must conduct site assessments to determine what kind of foundations[15] are possible and identify the scale of the project. The developer must consummate an agreement to sell the power it produces, identify a point of interconnection[16] to the power grid, and then prepare a construction and operation plan, which is subject to further environmental review[17]. All of that takes about five years, and it’s only the beginning.

For a project to move forward, developers may need to secure dozens of permits[18] from local, tribal, state, regional and federal agencies. The federal Bureau of Ocean Energy Management, which has jurisdiction[19] over leasing and management of the seabed, must consult with agencies that have regulatory responsibilities over different aspects in the ocean, such as the armed forces, Environmental Protection Agency and National Marine Fisheries Service, as well as groups including commercial and recreational fishing, Indigenous groups, shipping, harbor managers and property owners.

For Vineyard Wind I – which began sending power from five[20] of its 62 planned wind turbines off Martha’s Vineyard in early 2024 – the time from BOEM’s lease auction to getting its first electricity to the grid was about nine years.

Costs can balloon during the regulatory delays

Until recently, these contracts didn’t include any mechanisms to adjust for rising supply costs during the long approval time, adding to the risk for developers.

From the time today’s projects were bid to the time they were approved for construction, the world dealt with the COVID-19 pandemic, inflation, global supply chain problems, increased financing costs and the war in Ukraine. Steep increases in commodity prices, including for steel and copper[21], as well as in construction and operating costs, made many contracts signed years earlier no longer financially viable.

New and re-bid contracts are now allowing for price adjustments after the environmental approvals have been given, which is making projects more attractive to developers in the U.S. Many of the companies that canceled projects are now rebidding.

The regulatory process is becoming more streamlined[22], but it still takes about six years, while other countries are building[23] projects at a faster pace and larger scale.

Shipping rules, power connections

Another significant hurdle for offshore wind development in the U.S. involves a century-old law known as the Jones Act[24].

The Jones Act requires vessels carrying cargo between U.S. points to be U.S.-built, U.S.-operated and U.S.-owned. It was written to boost the shipping industry after World War I. However, there are only three offshore wind turbine installation vessels in the world that are large enough for the turbines proposed for U.S. projects, and none are compliant with the Jones Act.

That means wind turbine components must be transported by smaller barges from U.S. ports and then installed by a foreign installation vessel waiting offshore, which raises the cost and likelihood of delays.

A ship carrying three giant blades stacked atop each other.
A generator and blades head for the South Fork Wind farm from New London, Conn., on Dec. 4, 2023. AP Photo/Seth Wenig[25]

Dominion Energy is building a new ship, the Charybdis[26], that will comply with the Jones Act[27]. But a typical offshore wind farm needs over 25 different types of vessels – for crew transfers, surveying, environmental monitoring, cable-laying, heavy lifting and many other roles.

The nation also lacks a well-trained workforce[28] for manufacturing, construction and operation of offshore wind farms.

For power to flow from offshore wind farms, the electricity grid also requires significant upgrades. The Department of Energy is working on regional transmission plans[29], but permitting will undoubtedly be slow.

Lawsuits, disinformation add to the challenges

Numerous lawsuits from advocacy groups that oppose offshore wind projects have further slowed development.

Wealthy homeowners[30] have tried to stop wind farms that might appear in their ocean view. Astroturfing[31] groups that claim to be advocates of the environment, but are actually supported by fossil fuel industry interests[32], have launched disinformation campaigns[33].

In 2023, many Republican politicians and conservative groups immediately cast blame for whale deaths[34] off the coast of New York and New Jersey on the offshore wind developers, but the evidence points instead to increased ship traffic[35] collisions and entanglements with fishing gear.

Such disinformation can reduce public support and slow projects’ progress.

Efforts to keep the offshore wind industry going

The Biden administration set a goal to install 30 gigawatts[36] of offshore wind capacity by 2030, but recent estimates indicate that the actual number will be closer to half that[37].

Two people with their hair blowing in the wind look out at a small wind farm with very large wind turbines.
Passengers on a boat view America’s first offshore wind farm, owned by the Danish company Ørsted. Its five turbines generate power off Block Island, R.I. AP Photo/David Goldman[38]

Despite the challenges, developers have reason to move ahead.

The Inflation Reduction Act provides incentives, including federal tax credits[39] for the development of clean energy projects and for developers that build port facilities[40] in locations that previously relied on fossil fuel industries. Most coastal state governments are also facilitating projects by allowing for a price readjustment after environmental approvals have been given. They view offshore wind as an opportunity for economic growth.

These financial benefits can make building an offshore wind industry more attractive to companies that need market stability and a pipeline of projects to help lower costs – projects that can create jobs and boost economic growth and a cleaner environment.

References

  1. ^ began sending power (www.politico.com)
  2. ^ canceled contracts (www.energymonitor.ai)
  3. ^ sought to renegotiate them (www.politico.com)
  4. ^ US$16 million (www.bloomberg.com)
  5. ^ anticipating financial losses in 2024 (www.reuters.com)
  6. ^ more than 12 gigawatts of power (www.rtoinsider.com)
  7. ^ ESMAP/The World Bank via Wikimedia (en.wikipedia.org)
  8. ^ CC BY (creativecommons.org)
  9. ^ WindSTAR (www.uml.edu)
  10. ^ Center for Energy Innovation (www.uml.edu)
  11. ^ takes years (www.boem.gov)
  12. ^ purchases an expensive ocean lease (www.bsee.gov)
  13. ^ hundreds of millions of dollars (www.cnbc.com)
  14. ^ U.S. Department of the Interior, 2024 (www.bsee.gov)
  15. ^ what kind of foundations (aquaticbiosystems.biomedcentral.com)
  16. ^ identify a point of interconnection (news.bloomberglaw.com)
  17. ^ environmental review (www.boem.gov)
  18. ^ dozens of permits (www.nationalacademies.org)
  19. ^ which has jurisdiction (www.boem.gov)
  20. ^ began sending power from five (www.mass.gov)
  21. ^ including for steel and copper (fred.stlouisfed.org)
  22. ^ becoming more streamlined (www.doi.gov)
  23. ^ other countries are building (gwec.net)
  24. ^ the Jones Act (www.maritime.dot.gov)
  25. ^ AP Photo/Seth Wenig (newsroom.ap.org)
  26. ^ new ship, the Charybdis (www.dominionenergy.com)
  27. ^ comply with the Jones Act (www.prnewswire.com)
  28. ^ lacks a well-trained workforce (www.nrel.gov)
  29. ^ working on regional transmission plans (www.energy.gov)
  30. ^ Wealthy homeowners (www.theguardian.com)
  31. ^ Astroturfing (www.merriam-webster.com)
  32. ^ supported by fossil fuel industry interests (www.climatedevlab.brown.edu)
  33. ^ launched disinformation campaigns (www.americanprogress.org)
  34. ^ cast blame for whale deaths (whyy.org)
  35. ^ evidence points instead to increased ship traffic (www.fisheries.noaa.gov)
  36. ^ goal to install 30 gigawatts (www.whitehouse.gov)
  37. ^ closer to half that (www.bloomberg.com)
  38. ^ AP Photo/David Goldman (newsroom.ap.org)
  39. ^ federal tax credits (crsreports.congress.gov)
  40. ^ that build port facilities (home.treasury.gov)

Read more https://theconversation.com/why-us-offshore-wind-power-is-struggling-the-good-the-bad-and-the-opportunity-228983

How COVID changed our shopping habits for good & what it means for the future

As Aussies say online shopping ‘came to the rescue’ in 2020 & 60% believe it will be even more important in 2021    COVID-19 has chang...

Business Training

13 Top Advantages of Owning a Real Estate Photography Business

Starting a real estate photography business can be both rewarding and practical, especially for those who have a passion for photography and an in...

Business Training

9 Reasons To Hire An SEO Agency in Sydney (2)

Businesses across Sydney are now quickly coming out of lockdown. With 2022 just around the corner, it’s important that businesses adapt to the new...

Business Training

Is Maintaining Good Customer Service Difficult?

Good service is the key to success within any customer-facing business. Employees should strive to help in a clear and friendly way, to attract new ...

Business Training

Di Jones real estate recognises high achievers

Di Jones celebrated its outstanding performers on Saturday (24 February 2018) evening at the Di Jones Real Estate Annual Awards.                   ...

Business Training

Get into the property market: Buy a house with someone else and split the home loan. Find out the pros and cons

Split home loans are on the rise as more Aussies pool their cash to get into the property market to enjoy the wealth creating benefits of home own...

Property